PGRR145

Summary

Title Batch Zero Process for Large Load Interconnections
Next Group ROS
Next Step ROS for consideration
Status Pending

Action

Date Gov Body Action Taken Next Steps
04/02/2026 ROS Deferred/Tabled ROS for consideration

Voting Record

Date Gov Body Motion Result
04/02/2026 ROS To table PGRR145 Passed

Background

Status: Pending
Date Posted: Mar 4, 2026
Sponsor: ERCOT
Urgent: No
Sections: 2.1, 2.2, 3.1.2.1, 3.1.2, 3.1.3, 5.3.5, 6.6.1, 6.6.2, 6.6.3, 9, 9.1, 9.2.1, 9.2.1.1 (new), 9.2.1.2 (new), 9.2.1.3 (new), 9.2.1.4 (new), 9.2.2, 9.2.3, 9.2.4, 9.2.5, 9.3, 9.3.1, 9.3.2, 9.3.3 (delete), 9.3.4 (delete), 9.3.4.1 (delete), 9.3.4.2 (delete), 9.3.4.3 (delete), 9.4, 9.5, 9.5.1(delete), 9.5.2 (delete), 9.6, 9.7 (new), 9.7.1 (new), 9.7.2 (new), 9.7.3 (new), 9.7.4 (new), 9.7.5 (new), 9.8 (new), 9.8.1 (new), 9.8.2 (new), 9.8.3 (new), 9.8.4 (new), 9.8.4.1 (new), 9.8.4.2 (new), 9.8.4.3 (new), 9.9 (new), 9.10 (new), 9.10.1 (new), 9.10.2 (new)
Description: This Planning Guide Revision Request (PGRR) creates a transitional Batch Zero for ERCOT to study on a system-wide basis the reliability impacts of Large Loads that meet certain study maturity and commitment criteria.
Reason: Strategic Plan Objective 1