MIS LOG IN

NPRR533

Summary

Title PCRR Eligibility Requirements (formerly "Clarification of PCRR Eligibility Requirements")
Next Group
Next Step
Status Approved on 04/08/2014
Effective Dates
05/01/2014

Action

Date Gov Body Action Taken Next steps
04/08/2014 BOARD Approved
02/27/2014 TAC Recommended for Approval ERCOT Board consideration of NPRR533
02/13/2014 PRS Recommended for Approval TAC consideration of NPRR533
04/18/2013 PRS Deferred/Tabled PRS language consideration

Voting Record

Date Gov Body Motion Result
04/08/2014 BOARD To approve NPRR533 as recommended by TAC in the 2/27/14 TAC Report. Passed
02/27/2014 TAC To recommend approval of NPRR533 as recommended by PRS in the 2/13/14 PRS Report, as amended by the 2/26/14 San Bernard Electric Cooperative comments and as revised by TAC. Passed
02/13/2014 PRS To grant NPRR533 Urgent status and to forward NPRR533 to TAC. Passed
04/18/2013 PRS To table NPRR533 until the first PRS meeting after an ERCOT workshop on NPRR533 is held. Passed

Background

Status: Approved
Date Posted: Mar 29, 2013
Sponsor: ERCOT
Urgent: Yes
Sections: 3.4.2, 7.4, 7.4.1, 7.4.1.1 (new), 7.4.1.3 (new), 7.4.1.3.1 (new), 7.4.1.3.2 (new), 7.4.2, 7.4.2.1 (new), 7.4.2.2 (new)
Description: This Nodal Protocol Revision Request (NPRR) clarifies the eligibility for Pre-Assigned Congestion Revenue Rights (PCRRs) subject to changes over time in contracts, Entity relationships, and resource status and capabilities.
Reason: Additional clarity is needed in the ERCOT Protocols on the governing rules for PCRR eligibility as customer relationships have changed, resources are upgraded/mothballed/retired, and contracts are extended or terminated. ERCOT submits this NPRR to clarify the circumstances in which PCRRs will continue to be eligible versus when that eligibility is partially or totally forfeited.

Key Documents

Related Content