PGRR103

Summary

Title Establish Time Limit for Generator Commissioning Following Approval to Synchronize
Next Group ROS
Next Step Language Consideration
Status Pending

Action

Date Gov Body Action Taken Next steps
01/05/2023 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
01/05/2023 ROS to table PGRR103 and refer the issue to the Operations Working Group (OWG) and Planning Working Group (PLWG) Passed

Background

Status: Pending
Date Posted: Dec 21, 2022
Sponsor: ERCOT
Urgent: No
Sections: 5.5
Description: This Planning Guide Revision Request (PGRR) requires an Interconnecting Entity to complete all conditions for commercial operation of a Generation Resource or Energy Storage Resource (ESR) within 180 days of receiving approval for Initial Synchronization from ERCOT.
Reason: Addresses current operational issues