NPRR1143

Summary

Title Provide ERCOT Flexibility to Determine When ESRs May Charge During an EEA Level 3
Next Group
Next Step
Status Approved on 07/20/2023
Effective Dates
08/01/2023

Action

Date Gov Body Action Taken Next steps
07/20/2023 PUCT Approved
06/20/2023 BOARD Recommended for Approval Revision Request Consideration
05/23/2023 TAC Recommended for Approval Revision Request Consideration
05/10/2023 PRS Recommended for Approval Revision Request Consideration
04/13/2023 PRS Recommended for Approval Impact Analysis Consideration
08/11/2022 PRS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
07/20/2023 PUCT to approve NPRR1143 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Rules Adopted by the Independent Organization Passed
06/20/2023 BOARD to recommend approval of NPRR1143 as recommended by TAC in the 5/23/23 TAC Report Passed
05/23/2023 TAC to recommend approval of NPRR1143 as recommended by PRS in the 5/10/23 PRS Report as amended by the 5/19/23 ERCOT comments and the 5/22/23 Revised Impact Analysis Passed
05/10/2023 PRS to endorse and forward to TAC the 4/13/23 PRS Report and the 7/27/22 Impact Analysis for NPRR1143 Passed
04/13/2023 PRS to recommend approval of NPRR1143 as amended by the 9/29/22 ERCOT comments Passed
08/11/2022 PRS to table NPRR1143 and refer the issue to ROS and WMS Passed

Background

Status: Approved
Date Posted: Jul 27, 2022
Sponsor: ERCOT
Urgent: No
Sections: 6.5.9.4.2
Description: This Nodal Protocol Revision Request (NPRR) allows ERCOT the ability to decide when Energy Storage Resources (ESRs) may charge during an Energy Emergency Alert (EEA) Level 3.
Reason: Market efficiencies or enhancements