MIS LOG IN

NPRR1191

Summary

Title Registration, Interconnection, and Operation of Customers with Large Loads; Information Required of Customers with Loads 25 MW or Greater
Next Group PRS
Next Step PRS for consideration
Status Pending

Action

Date Gov Body Action Taken Next steps
09/13/2023 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
09/13/2023 PRS To table NPRR1191 Passed

Background

Status: Pending
Date Posted: Aug 1, 2023
Sponsor: ERCOT
Urgent: No
Sections: 2.1, 2.2, 3.1.1, 3.1.5.11, 3.2.6.2.1, 3.3.2, 3.15, 3.15.3, 3.22, 3.22.1, 3.22.1.1, 3.22.1.2, 3.22.1.3, 3.22.1.4 (new), 3.22.1.4, 3.22.2, 3.22.3, 6.5.7.3.1, 6.5.7.12 (new), 6.5.9.4.1, 16.20 (new), 16.20.1 (new), 23R (new), ERCOT Fee Schedule
Description: This Nodal Protocol Revision Request (NPRR) and the related PGRR, NOGRR, and RRGRR establish registration, interconnection, and operational requirements for Customers with “Large Loads”—defined in this NPRR to refer to Facilities with an aggregate peak power Demand of 75 MW or more. ERCOT proposes these requirements based upon its experience with the interim large Load interconnection process implemented on March 25, 2022, analysis of operational events, and the discussion of various issues concerning Large Loads explored by the Large Flexible Load Task Force (LFLTF). Although the primary focus of this NPRR is Loads that are 75 MW or larger, this NPRR also requires a Customer with an aggregate peak Demand of 25 MW or more at a site behind one or more common Points of Interconnection (POIs) or Service Delivery Points to provide ERCOT with information and Load parameter data that is specified in the accompanying RRGRR.
Reason: Strategic Plan Objective 1

Key Documents

Related Content