Summary

Title Proxy Energy Offer Curve
Next Group
Next Step
Status Approved on 09/21/2010
Effective Dates
12/01/2010

All sections except for Section 6.5.7.3(5)

02/04/2014

Section 6.5.7.3(5)

Action

Date Gov Body Action Taken Next steps
09/21/2010 BOARD Approved
09/02/2010 TAC Recommended for Approval ERCOT Board consideration of NPRR240
08/19/2010 PRS Recommended for Approval TAC consideration of NPRR240
06/17/2010 PRS Deferred/Tabled PRS language consideration
07/22/2010 PRS Recommended for Approval PRS Impact Analysis review

Voting Record

Date Gov Body Motion Result
09/21/2010 BOARD To approve NPRR240 as recommended by TAC in the 9/2/10 TAC Report. Passed
09/02/2010 TAC To recommend approval of NPRR240 as recommended by PRS in the 8/19/10 PRS Report with a priority of High/Medium for the grey-boxed language. Passed
08/19/2010 PRS To endorse and forward the 7/22/10 PRS Report and Impact Analysis for NPRR240 to TAC and to recommend a priority of High/Medium. Passed
06/17/2010 PRS To table NPRR240. Passed
07/22/2010 PRS To recommend approval of NPRR240 as amended by the 7/21/10 WMS comments and as revised by PRS. Passed

Background

Status: Approved
Date Posted: May 25, 2010
Sponsor: Potomac Economics
Urgent: No
Sections: 6.5.7.3
Description: This Nodal Protocol Revision Request (NPRR) states that the Entity with decision making authority over how a Resource or Split Generation Resource is offered or scheduled shall be responsible for all offers associated with each Resource, including offers represented by a proxy Energy Offer Curve. Additional non-substantive administrative revisions, such as correcting acronym usage, are shown with the author "ERCOT Market Rules."
Reason: Clarification of responsibility and accountability for energy offers.