MIS LOG IN

NPRR556

Summary

Title Resource Adequacy During Transmission Equipment Outage
Next Group
Next Step
Status Approved on 02/11/2014
Effective Dates
10/22/2015

Action

Date Gov Body Action Taken Next steps
02/11/2014 BOARD Approved
01/28/2014 TAC Recommended for Approval Board consideration
01/16/2014 PRS Recommended for Approval TAC Consideration
12/19/2013 PRS Recommended for Approval PRS Impact Analysis Consideration
07/18/2013 PRS Deferred/Tabled PRS Language Consideration

Voting Record

Date Gov Body Motion Result
02/11/2014 BOARD To approve NPRR556 as recommended by TAC in the 1/28/14 TAC Report Passed
01/28/2014 TAC To recommend approval of NPRR556 as recommended by PRS in the 1/16/14 PRS Report. Passed
01/16/2014 PRS To endorse and forward the 12/19/13 PRS Report and Impact Analysis for NPRR556 to TAC with a recommended priority of 2014 and rank of 1080. Passed
12/19/2013 PRS To recommend approval of NPRR556 as amended by the 12/16/13 ROS comments and to bring the Impact Analysis back to PRS for review. Passed
07/18/2013 PRS To table NPRR556 and refer the issue to ROS and WMS Passed

Background

Status: Approved
Date Posted: Jul 10, 2013
Sponsor: Tenaska Power Services
Urgent: Yes
Sections: 3.10.7.2
Description: This Nodal Protocol Revision Request (NPRR) adds a requirement for the Network Operations Model so that Resources that are being served by temporary equipment can participate in the ERCOT market as in normal operations.
Reason: To address Resource adequacy issues due to Network Operations Model problems.

Key Documents

Related Content