Summary

Title Voluntary Registration of Loads with Curtailable Load Capabilities
Next Group
Next Step
Status Approved on 07/31/2025

Action

Date Gov Body Action Taken Next Steps
07/31/2025 PUCT Approved
06/24/2025 BOARD Recommended for Approval Revision Request Consideration
06/12/2025 TAC Recommended for Approval Revision Request Consideration
05/28/2025 TAC Deferred/Tabled Revision Request Consideration
05/14/2025 PRS Recommended for Approval Revision Request Consideration
04/09/2025 PRS Deferred/Tabled Impact Analysis Consideration
03/12/2025 PRS Recommended for Approval Impact Analysis Consideration
07/18/2024 PRS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
07/31/2025 PUCT to approve NPRR1238 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization Passed
06/24/2025 BOARD to recommend approval of NPRR1238 as recommended by the 6/12/25 TAC Report and the 6/13/25 Revised Impact Analysis Passed
06/12/2025 TAC to recommend approval of NPRR1238 as recommended by PRS in the 5/14/25 PRS Report as amended by the 6/5/25 TIEC comments; and the 5/27/25 Revised Impact Analysis. Passed
05/28/2025 TAC to table NPRR1238 Passed
05/14/2025 PRS to endorse and forward to TAC the 4/9/25 PRS Report as amended by the 5/7/25 ERCOT comments and 5/13/25 Impact Analysis for NPRR1238 with a recommended priority of 2026 and rank of 4535 Passed
04/09/2025 PRS to table NPRR1238 Passed
03/12/2025 PRS to recommend approval of NPRR1238 as amended by the 2/25/25 Oncor comments Passed
07/18/2024 PRS to table NPRR1238 and refer the issue to ROS and WMS Passed

Background

Status: Approved
Date Posted: Jun 26, 2024
Sponsor: Golden Spread Electric Cooperative
Urgent: No
Sections: 2.1, 2.2, 3.2.6.2.1, 6.5.7.3.1, 6.5.9.4.1, 16.20 (new), 23T (new)
Description: This Nodal Protocol Revision Request (NPRR) introduces a new category of Voluntary Early Curtailment Load (VECL) and establishes a process by which Loads may operate as a VECL so that they can be accounted for differently in Load shed tables than other Loads.