NPRR1103

Summary

Title Securitization – PURA Subchapter M Default Charges
Next Group
Next Step
Status Approved on 12/16/2021
Effective Dates
12/17/2021

Phase 1

08/01/2023

All remaining sections

Action

Date Gov Body Action Taken Next steps
12/16/2021 PUCT Approved
12/10/2021 BOARD Recommended for Approval PUCT for Consideration
11/29/2021 TAC Recommended for Approval Board for consideration
11/10/2021 PRS Recommended for Approval TAC for consideration

Voting Record

Date Gov Body Motion Result
12/16/2021 PUCT To approve NPRR1103 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307, Review of Rules Adopted by the Independent Organization in Calendar Year 2021 Passed
12/10/2021 BOARD To recommended approval of NPRR1103 as recommended by TAC in the 11/29/21 TAC Report and the Revised Impact Analysis. Passed
11/29/2021 TAC To recommend approval of NPRR1103 as recommended by PRS in the 11/10/21 PRS Report with a recommended effective date of upon PUCT approval (12/17/21) for Phase 1 Passed
11/10/2021 PRS To grant NPRR1103 Urgent status; to recommend approval of NPRR1103 as amended by the 11/5/21 LCRA comments as revised by PRS; and to forward to TAC NPRR1103 and the Impact Analysis with a recommended priority of 2021 and rank of 320 Passed

Background

Status: Approved
Date Posted: Nov 1, 2021
Sponsor: ERCOT
Urgent: Yes
Sections: 2.1, 9.1.2, 16.11.4.7, 26 (new), 26.1 (new), 26.2 (new), 26.3 (new), 26.3.1 (new), 26.3.1.1 (new), 26.3.1.2 (new), 26.3.1 (new), 26.3.1.1 (new), 26.3.1.2 (new), 26.4 (new), 26.4 (new), 26.5 (new), 26.5.1 (new), 26.5.2 (new), 26.5.3 (new), 26.5.4 (new), 26.5.5 (new), 26.5.6 (new), 26.5.7 (new)
Description: This Nodal Protocol Revision Request (NPRR) establishes processes for the assessment and collection of Default Charges and Default Charge Escrow Deposits to QSEs and CRRAHs pursuant to the Debt Obligation Order (DOO) issued in Public Utility Commission of Texas (PUCT) Docket No. 52321, Application of Electric Reliability Council of Texas, Inc. for a Debt Obligation Order Pursuant to Chapter 39, Subchapter M, of PURA.
Reason: Regulatory requirements