MIS LOG IN

NPRR340

Summary

Title Introduction and Definition of Duration-Limited Resources (formerly "Unannounced HSL test for Duration-Limited Resources")
Next Group
Next Step
Status Withdrawn

Action

Date Gov Body Action Taken Next steps
10/23/2014 TAC Approved
08/04/2011 TAC Deferred/Tabled TAC consideration
07/07/2011 TAC Deferred/Tabled TAC for consideration.
06/02/2011 TAC Deferred/Tabled TAC for consideration.
05/19/2011 PRS Recommended for Approval TAC for consideration.
03/24/2011 PRS Deferred/Tabled PRS for consideration.

Voting Record

Date Gov Body Motion Result
10/23/2014 TAC To approve the Request for Withdrawal for NPRR340. Passed
08/04/2011 TAC To table NPRR340 Passed
07/07/2011 TAC To table NPRR340. Passed
06/02/2011 TAC To table NPRR340 for one month and to request WMS to reevaluate the inclusion of energy in the definition of DLR and to attempt to eliminate inconsistencies relative to testing between paragraphs (5) and (6) of Section 8.1.1.2.1.1. Passed
05/19/2011 PRS To recommend approval of NPRR340 as amended by the 5/18/11 ERCOT comments and to forward NPRR340 to TAC. Passed
03/24/2011 PRS To table NPRR340 Passed

Background

Status: Withdrawn
Date Posted: Mar 21, 2011
Sponsor: Praveen Kathpalon on behalf of AES
Urgent: Yes
Sections: 2.1, 3.17.2, 3.17.3, 8.1.1.2
Description: This Nodal Protocol Revision Request (NPRR) defines Duration-Limited Resource and amends the General Capacity Testing Requirements to reflect operational characteristics of this type of Resource.
Reason: Current testing requirements are designed for conventional Generation Resources, which provide unlimited energy and are able to participate in all markets. This NPRR defines Duration-Limited Resource and adjusts the test for this type of Resource.

Key Documents

Related Content