Summary

Title Related to SMOGRR027, Move OBD to Settlement Metering Operating Guide – EPS Metering Design Proposal
Next Group PRS
Next Step Impact Analysis Consideration
Status Pending

Action

Date Gov Body Action Taken Next steps
09/13/2023 PRS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
09/13/2023 PRS to recommend approval of NPRR1193 as submitted Passed

Background

Status: Pending
Date Posted: Aug 9, 2023
Sponsor: ERCOT
Urgent: No
Sections: 10.4.2
Description: This Nodal Protocol Revision Request (NPRR) changes the referenced location of the EPS Design Proposal Form, as it is moving from the Other Binding Document List into the Settlement Metering Operating Guide (SMOG).
Reason: Administrative