NPRR1161
Summary
Title | Clarify AVR Notification Requirements for IRRs |
---|---|
Next Group | PRS |
Next Step | Impact Analysis Consideration |
Status | Pending |
Action
Date | Gov Body | Action Taken | Next steps |
---|---|---|---|
03/08/2023 | PRS | Recommended for Approval | Impact Analysis Consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
03/08/2023 | PRS | to recommend approval of NPRR1161 as submitted | Passed |
Background
Status: | Pending |
---|---|
Date Posted: | Feb 7, 2023 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 6.5.5.1 |
Description: | This Nodal Protocol Revision Request (NPRR) clarifies that Intermittent Renewable Resources (IRRs), who remain synchronized to the ERCOT System but are not able to provide reactive power when not providing real power, do not have to notify ERCOT other than the Real-Time telemetered status. |
Reason: | Addresses current operational issues |
Key Documents
Feb 7, 2023 - docx - 41.4 KB
Feb 7, 2023 - docx - 31 KB
Mar 9, 2023 - xls - 100.5 KB
Mar 9, 2023 - docx - 43.4 KB