MIS LOG IN

SMOGRR024

Summary

Title Implement NPRR1020
Next Group
Next Step
Status Approved on 02/09/2021
Effective Dates
03/01/2021

Action

Date Gov Body Action Taken Next steps
02/09/2021 BOARD Approved
01/27/2021 TAC Recommended for Approval Revision Request Consideration
01/06/2021 WMS Recommended for Approval Revision Request Consideration
12/02/2020 WMS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
02/09/2021 BOARD to approve SMOGRR024 as recommended by TAC in the 1/27/21 TAC Report Passed
01/27/2021 TAC to recommend approval of SMOGRR024 as recommended by WMS in the 1/6/21 WMS Report Passed
01/06/2021 WMS to endorse and forward to TAC the 12/2/20 WMS Report, as amended by the 12/30/20 ERCOT comments, and the Revised Impact Analysis for SMOGRR024 Passed
12/02/2020 WMS to grant SMOGRR024 Urgent status, and to recommend approval of SMOGRR024 as revised by WMS Passed

Background

Status: Approved
Date Posted: Nov 24, 2020
Sponsor: Tesla
Urgent: Yes
Sections: 1.1, 1.5.1, 1.6.2, 1.7.1, 1.9 (new), 2, 2.2 (new), 3.2.1, 3.2.3, 4.1, 5.5 (new), 6.3.3, 6.5.4, 6.7.2, Appendices A, B, and D (new)
Description: This Settlement Meter Operating Guide Revision Request (SMOGRR) makes modifications to accommodate telemetered auxiliary Load and allows a site to comply with NPRR1020.
Reason: Market efficiencies or enhancements; Administrative; Regulatory requirements

Key Documents