PGRR098

Summary

Title: Consideration of Load Shed in Transmission Planning Criteria
Next Group:
Next Step:
Status: Approved on 05/12/2022

Action

Date Gov Body Action Taken Next Steps
05/12/2022 PUCT Approved
04/28/2022 BOARD Recommended for Approval Revision Request Consideration
04/13/2022 TAC Recommended for Approval Revision Request Consideration
03/03/2022 ROS Recommended for Approval Revision Request Consideration
02/07/2022 ROS Recommended for Approval Impact Analysis Consideration
12/02/2021 ROS Deferred/Tabled ROS for Consideration

Voting Record

Date Gov Body Motion Result
05/12/2022 PUCT to approve PGRR098 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization Passed
04/28/2022 BOARD to recommend approval of PGRR098 as recommended by TAC in the 4/13/22 TAC Report Passed
04/13/2022 TAC to recommend approval of PGRR098 as recommended by ROS in the 3/3/22 ROS Report; with a recommended effective date of January 1, 2024 for Section 4.1.1.8 and upon system implementation for the remainder of PGRR098 Passed
03/03/2022 ROS to endorse and forward to TAC the 2/7/22 ROS Report and Impact Analysis for PGRR098 Passed
02/07/2022 ROS to recommend approval of PGRR098 as amended by the 2/1/22 ERCOT comments Passed
12/02/2021 ROS To table PGRR98 and refer the issue to PLWG Passed

Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.

Background

Status: Approved
Date Posted: Nov 8, 2021
Sponsor: LCRA
Urgent: No
Sections: 4.1.1.1, 4.1.1.8 (new)
Description: This Planning Guide Revision Request (PGRR) adds language to the existing reliability performance criteria to allow a corrective action plan to be developed under certain outage scenarios.
Reason: Addresses current operational issues