OGRR223

Summary

Title Real Time Production Potential
Next Group
Next Step
Status Approved on 01/06/2010

Action

Date Gov Body Action Taken Next steps
01/06/2010 TAC Approved
11/05/2009 TAC Referred WMS Review
10/15/2009 ROS Recommended for Approval TAC Consideration
09/15/2009 OWG Recommended for Approval ROS Consideration
08/19/2009 OWG Deferred/Tabled OWG IA Review
07/27/2009 OWG Recommended for Approval OWG IA review
06/17/2009 OWG Deferred/Tabled OWG Consideration
05/20/2009 OWG Deferred/Tabled OWG Consideration

Voting Record

Date Gov Body Motion Result
01/06/2010 TAC To approve OGRR223 as recommended by ROS in the 10/15/09 ROS Recommendation Report and as revised by TAC Passed
11/05/2009 TAC To refer OGRR223 to WMS Passed
10/15/2009 ROS To recommend approval of OGRR223 as recommended by the OWG in the 9/15/09 OWG Recommendation Report. Passed
09/15/2009 OWG Consensus to forward the 8/19/09 OWG Recommendation Report and Impact Analysis to ROS
08/19/2009 OWG Consensus to table OGRR223 for one month
07/27/2009 OWG Consensus to recommend approval of OGRR223 as submitted.
06/17/2009 OWG Consensus to table OGRR223 for one month.
05/20/2009 OWG Consensus to table OGRR223 for one month.

Background

Status: Approved
Date Posted: Apr 17, 2009
Sponsor: Wind Coalition
Urgent: No
Sections: Attachment 8A: ERCOT Data Sets
Description: This Operating Guide Revision Request (OGRR) establishes a requirement for Wind-powered Generation Resources (WGRs) to telemeter a Real Time signal indicating the Real Time Production Potential (RTPP) which will be a function of wind and turbine availability at the time.
Reason: To provide ERCOT with information about the actual available wind generation for curtailed WGRs as well as additional information to tune the wind generation forecast models.