NPRR788

Summary

Title RMR Study Modifications
Next Group
Next Step
Status Approved on 10/11/2016
Effective Dates
10/12/2016

Action

Date Gov Body Action Taken Next steps
10/11/2016 BOARD Approved
09/29/2016 TAC Recommended for Approval Board for consideration
09/15/2016 PRS Recommended for Approval TAC for consideration
08/11/2016 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
10/11/2016 BOARD To approve NPRR788 as recommended by TAC in the 9/29/16 TAC Report Passed
09/29/2016 TAC To recommend approval of NPRR788 as recommended by PRS in the 9/15/16 PRS Report as amended by the 9/23/16 IMM comments; with a recommended effective date of October 12, 2016 Passed
09/15/2016 PRS To recommend approval of NPRR788 as amended by the 9/14/16 Luminant comments as revised by PRS; and to forward to TAC Passed
08/11/2016 PRS To grant NPRR788 Urgent status; to table NPRR788 and refer the issue to ROS and WMS Passed

Background

Status: Approved
Date Posted: Jul 7, 2016
Sponsor: LCRA
Urgent: Yes
Sections: 3.14.1.2 and 3.14.1.2.1
Description: This Nodal Protocol Revision Request (NPRR) modifies the requirement for Reliability Must-Run (RMR) studies to use anticipated peaks.
Reason: Addresses current operational issues. Market efficiencies/enhancements.