Summary

Title RPG Estimated Capital Cost Thresholds of Proposed Transmission Projects
Next Group
Next Step
Status Approved on 01/15/2026
Effective Dates
02/01/2026

Action

Date Gov Body Action Taken Next Steps
01/15/2026 PRS Approved
12/08/2025 BOARD Recommended for Approval Revision Request Consideration
11/19/2025 TAC Recommended for Approval Revision Request Consideration
11/12/2025 PRS Recommended for Approval Revision Request Consideration
10/08/2025 PRS Recommended for Approval Impact Analysis Consideration
03/12/2025 PRS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
01/15/2026 PRS to approve NPRR1274 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization Passed
12/08/2025 BOARD to recommend approval of NPRR1274 as recommended by TAC in the 11/19/25 TAC Report Passed
11/19/2025 TAC to recommend approval of NPRR1274 as recommended by PRS in the 11/12/25 PRS Report Passed
11/12/2025 PRS to endorse and forward to TAC the 10/8/25 PRS Report and 2/25/25 Impact Analysis for NPRR1274 Passed
10/08/2025 PRS to recommend approval of NPRR1274 as amended by the 8/20/25 Oncor comments Passed
03/12/2025 PRS to table NPRR1274 and refer the issue to ROS Passed

Background

Status: Approved
Date Posted: Feb 25, 2025
Sponsor: ERCOT
Urgent: No
Sections: 3.11.4.3
Description: This Nodal Protocol Revision Request (NPRR) updates the estimated capital cost for the tier classification rules used for the Regional Planning Group (RPG) process.
Reason: General system and/or process improvement(s)