Summary

Title Remove Requirements to Submit Emergency Operations Plans, Weatherization Plans, and Declarations of Summer/Winter Weather Preparedness
Next Group
Next Step
Status Approved on 01/26/2023
Effective Dates
01/27/2023

Action

Date Gov Body Action Taken Next steps
01/26/2023 PUCT Approved
12/20/2022 BOARD Recommended for Approval PUCT for consideration
12/05/2022 TAC Recommended for Approval Board for consideration
11/11/2022 PRS Recommended for Approval TAC for consideration

Voting Record

Date Gov Body Motion Result
01/26/2023 PUCT To approve NPRR1152 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Rules Adopted by the Independent Organization Passed
12/20/2022 BOARD To recommend approval of NPRR1152 as recommended by TAC in the 12/5/22 TAC Report with a proposed effective date of January 27, 2023 Passed
12/05/2022 TAC To recommend approval of NPRR1152 as recommended by PRS in the 11/11/22 PRS Report with a proposed effective date of January 20, 2023 Passed
11/11/2022 PRS To grant NPRR1152 Urgent status; to recommend approval of NPRR1152 as submitted; and to forward to TAC NPRR1152 and the 10/20/22 Impact Analysis Passed

Background

Status: Approved
Date Posted: Oct 20, 2022
Sponsor: ERCOT
Urgent: Yes
Sections: 1.3.1.1, 1.3.2.1, 3.21, 3.21.1, 22K, and 22O (delete)
Description: In light of the implementation of 16 TAC §§ 25.53 and 25.55, this Nodal Protocol Revision Request (NPRR) removes the Protocol requirements to submit emergency operations plans (“EOPs”), weatherization plans, and declarations of Summer/Winter weather preparedness in light of recent Public Utility Commission of Texas (PUCT) rules requiring submission of such information to ERCOT; revises procedures for submitting to ERCOT declarations of natural gas pipeline coordination for Resource Entities with natural gas Generation Resources; revises the list of items considered Protected Information in Section 1.3.1.1 to remove references to weatherization plans and add protections for information relating to weatherization activities submitted to or obtained by ERCOT in connection with 16 TAC § 25.55; and revises the list of ERCOT Critical Energy Infrastructure Information (ECEII) to clarify language concerning EOPs and add protections for information relating to weatherization activities submitted to or obtained by ERCOT in connection with PUCT rules and NERC Reliability Standards.
Reason: Administrative