MIS LOG IN

NPRR1140

Summary

Title Recovering Fuel Costs for Generation Above LSL During RUC-Committed Hours
Next Group
Next Step
Status Approved on 11/03/2022
Effective Dates
11/04/2022

Section 9.14.7

Action

Date Gov Body Action Taken Next steps
11/03/2022 PUCT Approved
10/18/2022 BOARD Recommended for Approval Revision Request Consideration
09/28/2022 TAC Recommended for Approval Revision Request Consideration
09/15/2022 PRS Recommended for Approval Revision Request Consideration
08/11/2022 PRS Recommended for Approval Impact Analysis Consideration
07/13/2022 PRS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
11/03/2022 PUCT to approve NPRR1140 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization Passed
10/18/2022 BOARD to recommend approval of NPRR1140 as recommended by TAC in the 9/28/22 TAC Report Passed
09/28/2022 TAC to recommend approval of NPRR1140 as recommended by PRS in the 9/15/22 PRS Report and the 9/27/22 Revised Impact Analysis; with a proposed effective date of 11/4/22 for Section 9.14.7 and upon system implementation for all remaining language Passed
09/15/2022 PRS to endorse and forward to TAC the 8/11/22 PRS Report and 6/7/22 Impact Analysis for NPRR1140 with a recommended priority of 2023 and rank of 3750 Passed
08/11/2022 PRS to recommend approval of NPRR1140 as amended by the 8/10/22 ERCOT comments Passed
07/13/2022 PRS to table NPRR1140 and refer the issue to WMS Passed

Background

Status: Approved
Date Posted: Jun 7, 2022
Sponsor: ERCOT
Urgent: No
Sections: 5.7.1.3 and 9.14.7
Description: This Nodal Protocol Revision Request (NPRR) proposes changes to permit Generation Resources recover their fuel costs when instructed to start due to a Reliability Unit Commitment (RUC) and operate above the Generation Resource’s Low Sustained Limit (LSL). Specifically, this NPRR makes the following changes: • Remove the Max (0) function from the Revenue Less Cost Above LSL During RUC-Committed Hours (RUCEXRR) equation for Resources that have been granted a fuel dispute; • Add a Reliability Unit Commitment Fuel Cost Adder (RUCFCA) to the Real-Time Energy Offer Curve Cost Cap (RTEOCOST) to represent the incremental cost of fuel for generation above LSL; and • Provide clarification to Protocol Section 9.14.7 to allow for the recovery of such fuel costs via RUC Settlements.
Reason: Addresses current operational issues; Market efficiencies or enhancements