MIS LOG IN

NPRR1124

Summary

Title Recovering Actual Fuel Costs through RUC Guarantee
Next Group
Next Step
Status Approved on 05/12/2022
Effective Dates
05/13/2022

Action

Date Gov Body Action Taken Next steps
05/12/2022 PUCT Approved
04/28/2022 BOARD Recommended for Approval Revision Request Consideration
04/13/2022 TAC Recommended for Approval Revision Request Consideration
04/06/2022 PRS Recommended for Approval Revision Request Consideration

Voting Record

Date Gov Body Motion Result
05/12/2022 PUCT to approve NPRR1124 and accompanying ERCOT Market Impact Statement as presented in Project No. 52934, Review of Rules Adopted by the Independent Organization Passed
04/28/2022 BOARD to recommend approval of NPRR1124 as recommended by TAC in the 4/13/22 TAC Report. There was one opposing vote Passed
04/13/2022 TAC to recommend approval of NPRR1124 as recommended by PRS in the 4/6/22 PRS Report with a recommended effective date of following PUCT approval – May 13, 2022 Passed
04/06/2022 PRS to grant NPRR1124 Urgent status; to recommend approval of NPRR1124 as submitted; and to forward to TAC NPRR1124 and the Impact Analysis Passed

Background

Status: Approved
Date Posted: Mar 9, 2022
Sponsor: ERCOT
Urgent: Yes
Sections: 9.14.7
Description: This Nodal Protocol Revision Request (NPRR) proposes a change to ensure Generation Resources recover their actual fuel costs when instructed to start due to a RUC. Specifically, this NPRR recommends that the Startup Price per start (SUPR) and the Minimum-Energy Price (MEPR), as defined in paragraph (6) of Section 5.7.1.1, RUC Guarantee, will be set to the Startup Cap (SUCAP) and the Minimum-Energy Cap (MECAP), respectively, utilizing the actual approved fuel price paid.
Reason: Addresses current operational issues; Market efficiencies or enhancements

Key Documents

Related Content