NOGRR256

Summary

Title Related to NPRR1191, Registration, Interconnection, and Operation of Customers with Large Loads; Information Required of Customers with Loads 25 MW or Greater
Next Group ROS
Next Step ROS for consideration
Status Pending

Action

Date Gov Body Action Taken Next steps
09/07/2023 ROS Deferred/Tabled ROS for consideration

Voting Record

Date Gov Body Motion Result
09/07/2023 ROS To table NOGRR256 Passed

Background

Status: Pending
Date Posted: Aug 1, 2023
Sponsor: ERCOT
Urgent: No
Sections: 2.11 (new), 4.5.3.1, 4.5.3.4 (new), and 4.5.3.4
Description: This Nodal Operating Guide Revision Request (NOGRR) establishes voltage ride-through requirements for Large Loads and Load-shedding processes for Large Loads that are registered as Registered Curtailable Loads.
Reason: Strategic Plan Objective 1