MIS LOG IN

NOGRR236

Summary

Title Related to NPRR1105, Option to Deploy Distribution Voltage Reduction Measures Prior to Energy Emergency Alert (EEA)
Next Group
Next Step
Status Approved on 12/16/2021
Effective Dates
12/17/2021

Action

Date Gov Body Action Taken Next steps
12/16/2021 PUCT Approved
12/10/2021 BOARD Recommended for Approval Revision Request Consideration
11/29/2021 TAC Recommended for Approval Revision Request Consideration
11/17/2021 ROS Recommended for Approval Revision Request Consideration

Voting Record

Date Gov Body Motion Result
12/16/2021 PUCT to approve NOGRR236 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307, Review of Rules Adopted by the Independent Organization in Calendar Year 2021 Passed
12/10/2021 BOARD to recommend approval of NOGRR236 as recommended by TAC in the 11/29/21 TAC Report Passed
11/29/2021 TAC to recommend approval of NOGRR236 as recommended by ROS in the 11/17/21 ROS Report Passed
11/17/2021 ROS to grant NOGRR236 Urgent status; to recommend approval of NOGRR236 as amended by the 11/8/21 STEC comments; and to forward to TAC NOGRR236 and the Impact Analysis Result: Passed Passed

Background

Status: Approved
Date Posted: Nov 4, 2021
Sponsor: ERCOT
Urgent: Yes
Sections: 4.5.3.1
Description: This NOGRR provides ERCOT the ability to instruct Transmission and/or Distribution Service Providers (TDSPs) to deploy any available distribution voltage reduction measures prior to ERCOT declaring an Energy Emergency Alert (EEA) if ERCOT determines it is possible that the deployment of these measures could avoid the need to declare an EEA and ERCOT does not expect to need these measures to reduce the amount of Load shedding that may be needed in EEA Level 3. These revisions also clarify the role of TDSPs in determining whether distribution voltage reduction should be implemented.
Reason: Addresses current operational issues; Regulatory requirements

Key Documents