NOGRR204

Summary

Title Related to NPRR989, BESTF-1 Energy Storage Resource Technical Requirements
Next Group
Next Step
Status Approved on 06/09/2020

Action

Date Gov Body Action Taken Next steps
06/09/2020 BOARD Approved
05/29/2020 TAC Recommended for Approval Board for consideration
05/11/2020 ROS Recommended for Approval TAC for consideration
03/09/2020 ROS Recommended for Approval ROS for Impact Analysis consideration
01/09/2020 ROS Deferred/Tabled ROS for consideration

Voting Record

Date Gov Body Motion Result
06/09/2020 BOARD To approve NOGRR204 as recommended by TAC in the 5/29/20 TAC Report Passed
05/29/2020 TAC To grant NOGRR204 Urgent status and recommend approval of NOGRR204 as recommended by ROS in the 5/11/20 ROS Report Passed
05/11/2020 ROS To endorse and forward to TAC the 3/9/20 ROS Report and Impact Analysis for NOGRR204 Passed
03/09/2020 ROS To recommend approval of NOGRR204 as amended by the 2/28/20 ERCOT comments Passed
01/09/2020 ROS To table NOGRR204 and refer the issue to the Operations Working Group (OWG) and the Performance, Disturbance, Compliance Working Group (PDCWG) Passed

Background

Status: Approved
Date Posted: Dec 16, 2019
Sponsor: ERCOT
Urgent: Yes
Sections: 2.2.5, 2.2.7, 2.2.8, 2.2.10, 2.3, 2.6.2, 2.7, 2.7.1, 2.7.2, 2.7.3.2, 2.7.3.3, 2.7.3.4, 2.7.3.5, 2.9, 2.9.1, 3.3.2.1, 3.3.2.2, 6.2.6.3.4, 8C, and 8J
Description: This Nodal Operating Guide Revision Request (NOGRR) establishes technical requirements for Energy Storage Resources (ESRs) in the following areas: Reactive Power capability, including performance requirements during transient voltage disturbances, and testing criteria; voltage ride-through requirements; frequency ride-through requirements; and Governor Dead-Band and droop setting requirements.
Reason: Addresses current operational issues. Market efficiencies or enhancements.