MIS LOG IN

NOGRR123

Summary

Title Revisions to Misoperations Reporting Requirements
Next Group
Next Step
Status Approved on 01/28/2014
Effective Dates
04/01/2014

Action

Date Gov Body Action Taken Next steps
01/28/2014 TAC Approved
01/09/2014 ROS Recommended for Approval TAC for consideration
12/17/2013 OWG Recommended for Approval ROS for consideration
10/16/2013 OWG Deferred/Tabled OWG for IA review
09/18/2013 OWG Recommended for Approval OWG for IA Review

Voting Record

Date Gov Body Motion Result
01/28/2014 TAC To approve NOGRR123 as recommended by ROS in the 1/9/14 ROS Report and as revised by TAC. Passed
01/09/2014 ROS To recommend approval of NOGRR123 as recommended by OWG in the 12/17/13 OWG Report and as amended by the 1/7/14 Oncor comments. Passed
12/17/2013 OWG Consensus to endorse and forward the the 9/18/13 OWG Report as amended by the 12/16/13 ERCOT comments and as revised by OWG and Impact Analysis for NOGRR123 to TAC. Passed
10/16/2013 OWG To table NOGRR123 for one month. Passed
09/18/2013 OWG To recommend approval of NOGRR123 as revised by OWG. Passed

Background

Status: Approved
Date Posted: Aug 29, 2013
Sponsor: OWG
Urgent: No
Sections: 6.2.2, 6.2.3, 8(B)
Description: This Nodal Operating Guide Revision Request (NOGRR) clarifies the reporting requirements for misoperations to ERCOT and Texas Reliability Entity (Texas RE).
Reason: To improve the reporting process of misoperations to ERCOT and Texas RE by specifying the frequency for reporting and clarifying how, and to what entities, the reporting should be made.

Key Documents