NOGRR123

Summary

Title Revisions to Misoperations Reporting Requirements
Next Group
Next Step
Status Approved on 01/28/2014
Effective Dates
04/01/2014

Action

Date Gov Body Action Taken Next Steps
01/28/2014 TAC Approved
01/09/2014 ROS Recommended for Approval TAC for consideration
12/17/2013 OWG Recommended for Approval ROS for consideration
10/16/2013 OWG Deferred/Tabled OWG for IA review
09/18/2013 OWG Recommended for Approval OWG for IA Review

Voting Record

Date Gov Body Motion Result
01/28/2014 TAC To approve NOGRR123 as recommended by ROS in the 1/9/14 ROS Report and as revised by TAC. Passed
01/09/2014 ROS To recommend approval of NOGRR123 as recommended by OWG in the 12/17/13 OWG Report and as amended by the 1/7/14 Oncor comments. Passed
12/17/2013 OWG Consensus to endorse and forward the the 9/18/13 OWG Report as amended by the 12/16/13 ERCOT comments and as revised by OWG and Impact Analysis for NOGRR123 to TAC. Passed
10/16/2013 OWG To table NOGRR123 for one month. Passed
09/18/2013 OWG To recommend approval of NOGRR123 as revised by OWG. Passed

Background

Status: Approved
Date Posted: Aug 29, 2013
Sponsor: OWG
Urgent: No
Sections: 6.2.2, 6.2.3, 8(B)
Description: This Nodal Operating Guide Revision Request (NOGRR) clarifies the reporting requirements for misoperations to ERCOT and Texas Reliability Entity (Texas RE).
Reason: To improve the reporting process of misoperations to ERCOT and Texas RE by specifying the frequency for reporting and clarifying how, and to what entities, the reporting should be made.