Title | Requirements for Interconnection Cost Reporting for Transmission-Connected Generators |
---|---|
Next Group | ROS |
Next Step | Language Consideration |
Status | Pending |
Action
Date | Gov Body | Action Taken | Next Steps |
---|---|---|---|
09/11/2025 | ROS | Deferred/Tabled | Language Consideration |
Voting Record
Date | Gov Body | Motion | Result |
---|---|---|---|
09/11/2025 | ROS | to table PGRR131 and refer the issue to the Planning Working Group (PLWG) | Passed |
Background
Status: | Pending |
---|---|
Date Posted: | Aug 26, 2025 |
Sponsor: | ERCOT |
Urgent: | No |
Sections: | 5.2.8.1 and 5.2.8.4 (new) |
Description: | This Planning Guide Revision Request (PGRR) implements mandatory reporting requirements for Transmission Service Providers (TSPs) and ERCOT for interconnection cost reporting for transmission-connected generators pursuant to paragraph (i) of P.U.C. Subst. R. 25.195, Terms and Conditions for Transmission Service, and deletes greybox language superseded by the requirements. Based on discussions with Public Utility Commission of Texas (PUCT) Staff, ERCOT encourages TSPs to review PUCT Project #58393, Annual Report on Dispatchable and Non-Dispatchable Generation Facilities, and to consider filing comments in that project if there are ways that the proposed annual reporting requirements in Project #58393 might be improved or aligned with the reporting requirements in paragraph (i) of P.U.C. Subst. R. 25.195. |
Reason: | Regulatory requirements |