PGRR120

Summary

Title SSO Prevention for Generator Interconnection
Next Group ROS
Next Step ROS for language consideration
Status Pending

Action

Date Gov Body Action Taken Next Steps
No updates have been made to this issue.

Voting Record

Date Gov Body Motion Result
No updates have been made to this issue.

Background

Status: Pending
Date Posted: Oct 14, 2024
Sponsor: ERCOT
Urgent: No
Sections: 5.2.10 (new)
Description: This Planning Guide Revision Request (PGRR) prevents generators from interconnecting to the ERCOT Transmission Grid if the generator would be radial to a series capacitor under N-1 conditions.
Reason: Strategic Plan Objective 1

Key Documents