PGRR110

Summary

Title Revision to Accommodate Steady-State Node-Breaker Modeling
Next Group ROS
Next Step Impact Analysis Consideration
Status Pending

Action

Date Gov Body Action Taken Next steps
09/07/2023 ROS Recommended for Approval Impact Analysis Consideration
08/03/2023 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
09/07/2023 ROS to recommend approval of PGRR110 as submitted Passed
08/03/2023 ROS to table PGRR110 and refer the issue to the Steady State Working Group (SSWG) Passed

Background

Status: Pending
Date Posted: Jul 19, 2023
Sponsor: ERCOT
Urgent: No
Sections: 6.1
Description: This Planning Guide Revision Request (PGRR) removes paragraph (2)(a) of Section 6.1 to accommodate the release of steady-state planning models in node-breaker format pursuant to System Change Request (SCR) 789, Update NMMS Topology Processor to PSSE 34 Capability.
Reason: Market efficiencies or enhancements