MIS LOG IN

PGRR089

Summary

Title Planning Data and Information Updates for Planning Posting
Next Group
Next Step
Status Approved on 08/19/2021

Action

Date Gov Body Action Taken Next steps
08/19/2021 PUCT Approved
08/10/2021 BOARD Recommended for Approval PUCT for consideration
06/23/2021 TAC Recommended for Approval Revision Request Consideration
06/03/2021 ROS Recommended for Approval Revision Request Consideration
04/29/2021 ROS Recommended for Approval Impact Analysis Consideration
04/01/2021 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
08/19/2021 PUCT to approve PGRR089 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307. Passed
08/10/2021 BOARD To recommend approval of PGRR089 as recommended by TAC in the 6/23/21 TAC Report and the Revised Impact Analysis Passed
06/23/2021 TAC to recommend approval of PGRR089 as recommended by ROS in the 6/3/21 ROS Report Passed
06/03/2021 ROS to endorse and forward to TAC the 4/29/21 ROS Report and the Impact Analysis for PGRR089 Passed
04/29/2021 ROS to recommend approval of PGRR089 as revised by ROS Passed
04/01/2021 ROS to table PGRR089 and refer the issue to Planning Working Group (PLWG) Passed

Background

Status: Approved
Date Posted: Mar 17, 2021
Sponsor: ERCOT
Urgent: No
Sections: 7.1
Description: This Planning Guide Revision Request (PGRR) makes changes to the list of data sets posted to the Market Information System (MIS) in Planning Guide Section 7.1. First, it removes the Planning Horizon Transmission Capability Methodology. Second, it adds Long-Term System Assessment (LTSA) postings, Geomagnetic Disturbance (GMD) vulnerability assessments, and the monthly Generator Interconnection Status (GIS) Report to the list.
Reason: Market efficiencies or enhancements, Administrative, Other: Retirement of NERC Reliability Standard FAC-013-2

Key Documents

Related Content