PGRR028

Summary

Title Evaluation of Compliance with Reactive Requirements
Next Group
Next Step
Status Withdrawn

Action

Date Gov Body Action Taken Next steps
06/05/2014 ROS Approved
11/14/2013 ROS Deferred/Tabled ROS for consideration.
10/23/2013 PLWG Recommended for Approval ROS for consideration.
09/25/2013 PLWG Recommended for Approval PLWG for Impact Analysis review.
03/27/2013 PLWG Deferred/Tabled PLWG Language Consideration
02/27/2013 PLWG Deferred/Tabled PLWG Language Consideration

Voting Record

Date Gov Body Motion Result
06/05/2014 ROS To approve the Request for Withdrawal of PGRR028. Passed
11/14/2013 ROS To table PGRR028 and refer the issue to PLWG. Passed
10/23/2013 PLWG Consensus to endorse and forward the 9/25/13 PLWG Report as amended by the 10/14/13 CenterPoint Energy comments and the Impact Analysis for PGRR028 to ROS.
09/25/2013 PLWG Consensus to recommend approval of PGRR028 as amended by the 9/23/13 ERCOT comments and as revised by the PLWG.
03/27/2013 PLWG Consensus to table PGRR028
02/27/2013 PLWG To table PGRR028 for one month

Background

Status: Withdrawn
Date Posted: Feb 12, 2013
Sponsor: ERCOT
Urgent: No
Sections: 5.6.1 (new)
Description: This Planning Guide Revision Request (PGRR) defines ERCOT’s process for evaluation proposed Generation Resources’ ability to provide reactive power. Protocol Section 3.15, Voltage Support, defines reactive capability requirements for Generation Resources. Paragraph (3) of Protocol Section 16.5, Registration of a Resource Entity requires ERCOT to opine upon the capability of the proposed Generation Resource’s ability to meet these requirements.
Reason: This PGRR is in response to concerns raised during the October 15, 2012 Photovoltaic and Storage Workshop. This PGRR proposes to clarify how proposed Generation Resources must design its new facilities.