NPRR965
Summary
| Title | GREDP Shutdown Exemption |
|---|---|
| Next Group | |
| Next Step | |
| Status | Approved on 12/10/2019 |
Action
| Date | Gov Body | Action Taken | Next Steps |
|---|---|---|---|
| 12/10/2019 | BOARD | Approved | |
| 10/23/2019 | TAC | Recommended for Approval | Revision Request Consideration |
| 10/10/2019 | PRS | Recommended for Approval | Revision Request Consideration |
| 09/12/2019 | PRS | Recommended for Approval | Impact Analysis Consideration |
Voting Record
| Date | Gov Body | Motion | Result |
|---|---|---|---|
| 12/10/2019 | BOARD | to approve NPRR965 as recommended by TAC in the 10/23/19 TAC Report | Passed |
| 10/23/2019 | TAC | to recommend approval of NPRR965 as recommended by PRS in the 10/10/19 PRS Report | Passed |
| 10/10/2019 | PRS | to endorse and forward to TAC the 9/12/19 PRS Report and Impact Analysis for NPRR965 with a recommended priority of 2020 and a rank of 2900 | Passed |
| 09/12/2019 | PRS | to recommend approval of NPRR965 as submitted | Passed |
Background
| Status: | Approved |
|---|---|
| Date Posted: | Aug 5, 2019 |
| Sponsor: | Luminant Generation Company LLC |
| Urgent: | No |
| Sections: | 8.1.1.4.1 |
| Description: | This Nodal Protocol Revision Request (NPRR) excludes from the Generation Resource Energy Deployment Performance (GREDP) calculation the five-minute intervals in which a Quick Start Generation Resource (QSGR) is engaging in the decommitment process under Section 3.8.3.1, Quick Start Generation Resource Decommitment Decision Process, or telemetering SHUTDOWN status. |
| Reason: | Addresses current operational issues; Administrative; Regulatory requirements |
Key Documents
Aug 5, 2019 - doc - 122 KB
Sep 17, 2019 - docx - 46.5 KB
Oct 8, 2019 - docx - 28.4 KB
Oct 15, 2019 - docx - 46.4 KB
Oct 28, 2019 - docx - 47.7 KB
Dec 12, 2019 - docx - 48.9 KB