Agenda
| 1. |
Antitrust Admonition |
M. Henson |
| 2. |
Approval of Minutes (Vote) |
M. Henson |
| August 15, 2019 |
||
| 3. |
TAC and Board Reports |
M. Henson |
| 4. |
Project Update and Summary of Project Priority List (PPL) Activity to Date |
T. Anderson |
| 5. |
Review PRS Reports, Impact Analyses, and Prioritization (Vote) (*) denotes no impact |
M. Henson |
| NPRR918, Validation for PTP Obligations with Links to an Option |
||
| NPRR936, CRR Account Holder Limits |
||
| NPRR941, Create a Lower Rio Grande Valley Hub |
||
| NPRR958, Modifications to Wind and Solar Capacity Calculations in the CDR |
||
| NPRR959, Creation of a Panhandle Region for Calculation of Seasonal Peak Average Capacity Contributions for Wind |
||
| NPRR960, Phased Approach and Clarifications for NPRR863, Creation of ERCOT Contingency Reserve Service and Revisions to Responsive Reserve* |
||
| NPRR961, Related to NOGRR194, Relocate Black Start Training Attendance Requirements to Nodal Operating Guides* |
||
| NPRR962, Publish Approved DC Tie Schedules |
||
| SCR804, ERCOT GridGeo Access for Transmission Operators |
||
| 6. |
Revision Requests Tabled at PRS (Possible Vote) |
M. Henson |
| NPRR826, Mitigated Offer Caps for RMR Resources |
||
| NPRR838, Updated O&M Cost for RMR Resources |
||
| NPRR849, Clarification of the Range of Voltage Set Points at a Generation Resource’s POI |
||
| NPRR902, ERCOT Critical Energy Infrastructure Information |
||
| NPRR903, Day-Ahead Market Timing Deviations |
||
| NPRR919, Exemption from Governor Primary Frequency Response Control for Certain Resources in Private Use Networks |
||
| NPRR928, Cybersecurity Incident Notification |
||
| NPRR933, Reporting of Demand Response by Retail Electric Providers and Non-Opt-In Entities |
||
| NPRR934, Advance Action Notice (AAN) and Clarify Process for Resource Outage Approval Withdrawal |
||
| NPRR937, Distribution Voltage Level Block Load Transfer (BLT) Deployment |
||
| NPRR938, Distribution Voltage Level Block Load Transfer (BLT) Compensation |
||
| NPRR945, Net Metering Requirements |
||
| NPRR946, Allow TDSPs to Use 814_28, Complete Un-executable Transactions for 814_03 Switch Transactions Involved In A Mass Transition Event |
||
| NPRR947, Clarification to Ancillary Service Supply Responsibility Definition and Improvements to Determining and Charging for Ancillary Service Failed Quantities |
||
| NPRR950, Switchable Generation Resources Providing Black Start Service |
||
| NPRR953, Addition of Relay Loadability Rating Definition |
||
| NPRR955, Define Limited Impact Remedial Action Scheme (RAS) |
||
| NPRR956, Designation of Providers of Transmission Additions |
||
| NPRR957, RTF-4 Create Definition and Terms for Energy Storage |
||
| NPRR963, Creation of Generation and Controllable Load Resource Group (GCLR Group) |
||
| NPRR964, Improvement of RMR Process and Removal of Synchronous Condenser Unit and Agreement |
||
| SCR800, Addition of DC Tie Ramp to GTBD Calculation |
||
| 7. |
Review of Revision Request Language (Vote) |
M. Henson |
| NPRR965, GREDP Shutdown Exemption |
||
| NPRR966, Changes to Support Reactive Power Coordination Tool |
||
| NPRR967, Allow Limited Duration Resource Energy Offer Curve Updates Near Real-Time and Remove the 10 MW Limit |
||
| NPRR968, Revise EEA Level 3 Triggers from 1375 MW to 1430 MW to Align with New Most Severe Single Contingency Value |
||
| NPRR969, Clean-up of Protocol 19.8, Retail Market Testing |
||
| SCR805, Provide Early Access to Certain 60-Day Reports to TSPs Upon Request |
||
| 8. |
Resource Definition Task Force (RTF) |
B. Wittmeyer |
| 9. |
Other Business |
M. Henson |
| TAC Subcommittee Structural Review |
||
| 2020 Meeting Schedule |
||
| Adjourn |
M. Henson |
Scheduled PRS Meetings
- Jul 17, 2019 - PRS Meeting
- Aug 15, 2019 - PRS Meeting
- Sep 12, 2019 - PRS Meeting
- Oct 10, 2019 - PRS Meeting
- Nov 13, 2019 - PRS Meeting
- Dec 12, 2019 - PRS Meeting
- Jan 16, 2020 - PRS Meeting
Key Documents
All information is posted as Public in accordance with the ERCOT Websites Content Management Corporate Standard.