MIS LOG IN

NPRR715

Summary

Title Clarification of Generator Modeling in the Market System
Next Group
Next Step
Status Approved on 12/08/2015
Effective Dates
01/01/2016

Action

Date Gov Body Action Taken Next steps
12/08/2015 BOARD Approved
10/29/2015 TAC Recommended for Approval Board for consideration
10/15/2015 PRS Recommended for Approval TAC for consideration
09/10/2015 PRS Recommended for Approval PRS for Impact Analysis review
07/16/2015 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
12/08/2015 BOARD To approve NPRR715 as recommended by TAC in the 10/29/15 TAC Report Passed
10/29/2015 TAC To recommend approval of NPRR715 as recommended by PRS in the 10/15/15 PRS Report Passed
10/15/2015 PRS To endorse and forward to TAC the 9/10/15 PRS Report and Impact Analysis for NPRR715 Passed
09/10/2015 PRS To recommend approval of NPRR715 as submitted Passed
07/16/2015 PRS To table NPRR715 and refer the issue to WMS Passed

Background

Status: Approved
Date Posted: Jul 1, 2015
Sponsor: ERCOT
Urgent: No
Sections: 2.1, 3.8.2, 4.5.1, and 6.5.7.3
Description: This Nodal Protocol Revision Request (NPRR) clarifies the modeling of Resources and brings the Protocols into better alignment with the current market systems by creating a new defined term, Resource Connectivity Node, and specifying that energy injection is at that node.
Reason: Administrative. Increases the transparency of generator modeling in the current market systems.

Key Documents

Related Content