MIS LOG IN

NPRR715

Summary

Title: Clarification of Generator Modeling in the Market System
Next Group:
Next Step:
Status: Approved on 12/08/2015
Effective Dates:
01/01/2016

Action

Date Gov Body Action Taken Next Steps
12/08/2015 BOARD Approved
10/29/2015 TAC Recommended for Approval Board for consideration
10/15/2015 PRS Recommended for Approval TAC for consideration
09/10/2015 PRS Recommended for Approval PRS for Impact Analysis review
07/16/2015 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
12/08/2015 BOARD To approve NPRR715 as recommended by TAC in the 10/29/15 TAC Report Passed
10/29/2015 TAC To recommend approval of NPRR715 as recommended by PRS in the 10/15/15 PRS Report Passed
10/15/2015 PRS To endorse and forward to TAC the 9/10/15 PRS Report and Impact Analysis for NPRR715 Passed
09/10/2015 PRS To recommend approval of NPRR715 as submitted Passed
07/16/2015 PRS To table NPRR715 and refer the issue to WMS Passed

Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.

Background

Status: Approved
Date Posted: Jul 1, 2015
Sponsor: ERCOT
Urgent: No
Sections: 2.1, 3.8.2, 4.5.1, and 6.5.7.3
Description: This Nodal Protocol Revision Request (NPRR) clarifies the modeling of Resources and brings the Protocols into better alignment with the current market systems by creating a new defined term, Resource Connectivity Node, and specifying that energy injection is at that node.
Reason: Administrative. Increases the transparency of generator modeling in the current market systems.

Key Documents