NPRR534

Summary

Title: Clarification of QSE Responsibilities to Provide Service in NOIE Territory
Next Group:
Next Step:
Status: Approved on 05/14/2013
Effective Dates:
06/01/2013

Action

Date Gov Body Action Taken Next Steps
05/14/2013 BOARD Approved
05/02/2013 TAC Recommended for Approval ERCOT Board consideration of NPRR534
04/18/2013 PRS Recommended for Approval TAC consideration of NPRR534

Voting Record

Date Gov Body Motion Result
05/14/2013 BOARD To approve NPRR534 as recommended by TAC in the 5/2/13 TAC Report. Passed
05/02/2013 TAC To recommend approval of NPRR534 as recommended by PRS in the 4/18/13 PRS Report. Passed
04/18/2013 PRS To recommend approval of NPRR534 as submitted and to forward NPRR534 to TAC. Passed

Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.

Background

Status: Approved
Date Posted: Apr 3, 2013
Sponsor: STEC, CPS Energy, Kerrville Public Utilities Board, Rayburn Country Electric Coop, Golden Spread Electric Coop and on behalf of Denton Municipal Electric
Urgent: Yes
Sections: 16.2.3, 16.5.2, 22G
Description: This Nodal Protocol Revision Request (NPRR) provides clarity that third party Qualified Scheduling Entities (QSEs) offering services within a Non-Opt-In Entity (NOIE) service territory require NOIE authorization.
Reason: Load Resource and ERS services are provided by QSEs rather than a Load Serving Entity (LSE). Some third party QSEs are confused as to who is authorized to provide the service in NOIE areas. This NPRR clarifies that a NOIE is the default provider and at its sole discretion may authorize third party QSEs to provide Load Resource and ERS services within their service territory.