Summary

Title Resolution of Alignment Items A175 and A176 - Settlement of Generation Resources Dispatched to Meet System Reliability Requirements
Next Group
Next Step
Status Approved on 10/19/2010
Effective Dates
12/01/2010

or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (11/01/10 Nodal Protocols Library)

Action

Date Gov Body Action Taken Next steps
10/19/2010 BOARD Approved
10/07/2010 TAC Recommended for Approval ERCOT Board consideration of NPRR259
10/04/2010 PRS Recommended for Approval TAC consideration of NPRR259
09/23/2010 PRS Recommended for Approval PRS Impact Analysis review
08/19/2010 PRS Deferred/Tabled PRS language consideration

Voting Record

Date Gov Body Motion Result
10/19/2010 BOARD To approve NPRR259 as recommended by TAC in the 10/7/10 TAC Report. Passed
10/07/2010 TAC To recommend approval of NPRR259 as recommended by PRS in the 10/4/10 PRS Report. Passed
10/04/2010 PRS To endorse and forward the 9/23/10 PRS Report and Impact Analysis for NPRR259 to TAC. Passed
09/23/2010 PRS To recommend approval of NPRR259 as amended by the 9/1/10 ERCOT comments and as revised by PRS. Passed
08/19/2010 PRS To table NPRR259. Passed

Background

Status: Approved
Date Posted: Jul 27, 2010
Sponsor: ERCOT
Urgent: No
Sections: 5.1, 6.5.9.4.1
Description: This Nodal Protocol Revision Request (NPRR) clarifies that all commitments of a specific Generation Resource in response to an ERCOT Dispatch Instruction (whether issued electronically or verbally) for the commitment of that Generation Resource will be considered to be a Reliability Unit Commitment (RUC) and will be settled in accordance with the RUC Settlement provisions described in the Nodal Protocols.
Reason: This change conforms the Nodal Protocols to the as-built ERCOT systems implementation and administrative controls.

Key Documents