NOGRR089
Summary
| Title | Clarification of Responsibilities for Black Start Resources and QSEs | 
|---|---|
| Next Group | |
| Next Step | |
| Status | Approved on 06/28/2012 | 
| Effective Dates | 
                   07/01/2012 
                   | 
            
Action
| Date | Gov Body | Action Taken | Next Steps | 
|---|---|---|---|
| 06/28/2012 | TAC | Approved | |
| 06/14/2012 | ROS | Recommended for Approval | TAC Consideration | 
| 05/16/2012 | OWG | Recommended for Approval | ROS Consideration | 
| 04/18/2012 | OWG | Recommended for Approval | OWG IA Review | 
| 02/15/2012 | OWG | Deferred/Tabled | OWG Consideration | 
| 01/30/2012 | OWG | Deferred/Tabled | OWG Language Consideration | 
Voting Record
| Date | Gov Body | Motion | Result | 
|---|---|---|---|
| 06/28/2012 | TAC | To approve NOGRR089 as recommended by ROS in the 6/14/12 ROS Report | Passed | 
| 06/14/2012 | ROS | To recommend approval of NOGRR089 as recommended by OWG in the 5/16/12 OWG Report | Passed | 
| 05/16/2012 | OWG | Consensus to endorse and forward the 4/18/12 OWG Report and Impact Analysis to ROS | |
| 04/18/2012 | OWG | Consensus to recommend approval of NOGRR089 as revised by the 4/3/12 BSWG comments | |
| 02/15/2012 | OWG | Consensus to table for one month | |
| 01/30/2012 | OWG | Consensus to table NOGRR089 for one month | 
Background
| Status: | Approved | 
|---|---|
| Date Posted: | Dec 14, 2011 | 
| Sponsor: | Luminant | 
| Urgent: | No | 
| Sections: | 4.6, 4.6.4, 8E, 9.4.2 | 
| Description: | This Nodal Operating Guide Revision Request (NOGRR) clarifies the responsibilities of the Black Start Resource and the Qualified Scheduling Entity (QSE) representing the Black Start Resource. It also clarifies language related to the Transmission Operator’s (TO’s) local Black Start plans and the QSE's Black Start procedures. | 
| Reason: | The local Black Start plan is developed by the appropriate TO and then is incorporated into the ERCOT Black Start Plan. The QSE provides a support role, as needed, during a Partial Blackout or a Blackout of the ERCOT System but may not be directly involved in the initial activities associated with a Black Start Resource when TOs and ERCOT are communicating directly with the Black Start Resource. | 
Key Documents
                Dec 14, 2011 - doc - 87 KB
            
        
                Jan 23, 2012 - doc - 37.5 KB
            
        
                Feb 1, 2012 - doc - 95 KB
            
        
                Feb 16, 2012 - doc - 95.5 KB
            
        
                Mar 28, 2012 - doc - 78 KB
            
        
                Apr 3, 2012 - doc - 80.5 KB
            
        
                Apr 20, 2012 - doc - 100 KB
            
        
                May 1, 2012 - doc - 54.5 KB
            
        
                May 21, 2012 - doc - 100 KB
            
        
                Jun 15, 2012 - doc - 102 KB
            
        
                Jun 29, 2012 - doc - 103.5 KB