MIS LOG IN

NOGRR033

Summary

Title Alignment with NPRR203, Amend Telemetry Bus Accuracy Requirements
Next Group
Next Step
Status Approved on 05/06/2010
Effective Dates
12/01/2010

or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (06/01/10 Nodal Operating Guide Library)

Action

Date Gov Body Action Taken Next steps
05/06/2010 TAC Approved
04/12/2010 ROS Recommended for Approval TAC Consideration
03/17/2010 OWG Recommended for Approval ROS Consideration
02/19/2010 OWG Recommended for Approval OWG IA Review
01/18/2010 OWG Deferred/Tabled OWG for language consideration.

Voting Record

Date Gov Body Motion Result
05/06/2010 TAC To approve NOGRR033 as recommended by ROS in the 4/12/10 ROS Recommendation Report Passed
04/12/2010 ROS To recommend approval of NOGRR033 as recommended by OWG in the 3/17/10 OWG Recommendation Report Passed
03/17/2010 OWG Consensus to endorse and forward the 2/19/10 OWG Recommendation Report and the Impact Analysis for NOGRR033 to ROS
02/19/2010 OWG Consensus to recommend approval of NOGRR033 as submitted
01/18/2010 OWG Consensus to table NOGRR033 for one month

Background

Status: Approved
Date Posted: Dec 22, 2009
Sponsor: Ebby John on behalf of the Network Data Support Working Group (NDSWG)
Urgent: No
Sections: 9.3.1
Description: This Nodal Operating Guide Revision Request (NOGRR) aligns the Nodal Operating Guides with changes proposed by Nodal Protocol Revision Request (NPRR) 203, Amend Telemetry Bus Accuracy Requirements, which clarifies the type of equipment being reported.
Reason: "Electrical Bus" is not the correct term to describe the way this item is being or could be monitored. This data is generated from the State Estimator (SE) and the term State Estimator Bus should be given a unique definition for this case. Being more specific will mitigate ambiguity about the way this item should and will be reported.

Key Documents