MIS LOG IN

RMGRR079

Summary

Title Changes to Support Revisions to the PUCT POLR and Expedited Switch Rules
Next Group
Next Step
Status Approved on 08/18/2009
Effective Dates
08/18/2009

Sections 7.2.2.1.1, 7.2.5, 7.2.5.1, 7.5, 7.5.1, 7.5.1.1, 7.5.1.2, 7.6.3.3, 7.6.5.1, 7.6.7.2, 7.11.3, 8.3.1.3, 8.3.3.3, Appendix F2, and Appendix G

03/29/2010

Sections 7.11.5.2.2 and 7.11.5.2.3

Action

Date Gov Body Action Taken Next steps
08/18/2009 BOARD Approved
08/06/2009 TAC Recommended for Approval Board of Directors for consideration.
07/15/2009 RMS Recommended for Approval TAC for consideration.

Voting Record

Date Gov Body Motion Result
08/18/2009 BOARD To approve RMGRR079 as amended by the 8/10/09 ERCOT comments. Passed
08/06/2009 TAC To recommend approval of RMGRR079 as amended by 7/24/09 MTTF comments with an effective date of "Upon ERCOT Board approval", except for changes to Section 7.11.5.2.2, Section 7.11.5.2.3, and "Timing/Business Rules for 814_06 Drop Due to Switch/Move-In Request" and "Example for 814_08, Cancel Switch/Move-In/Move-Out/Mass Transition Drop Request" in Appendix D, Transaction Timing Matrix, which would be effective upon system implementation. All Market Segments were present for the vote. Passed
07/15/2009 RMS To recommend approval of RMGRR079 as amended by the Reliant Energy Retail Services comments and the MTTF comments and as revised by RMS. RMS also voted to recommend that RMGRR079 be effective upon ERCOT Board approval of PRR819 with the exception of the changes to the following sections, which would be effective upon system implementation: Section 7.11.5.2.2, ERCOT, Section 7.11.5.2.3, TDSP, and "Timing/Business Rules for 814_06, Drop Due to Switch/Move-In Request" and "Example for 814_08, Cancel Switch/Move-In/Move-Out/Mass Transition Drop Request" in Appendix D, Transaction Timing Matrix. Passed

Background

Status: Approved
Date Posted: Jun 28, 2009
Sponsor: Jennifer Frederick on behalf of the Texas Standard Electronic Transaction (Texas SET) Working Group
Urgent: Yes
Sections: 7.2.2.1.1, 7.5, 7.5.1, 7.5.1.1, 7.5.1.2, 7.6.3.3, 7.6.5.1, 7.6.7.2, 7.11.3, 7.11.5.2.2, 7.11.5.2.3, 8.3.1.3, 8.3.3.3, 9, Appendix D, F2, G
Description: This Retail Market Guide Revision Request (RMGRR) provides that ERCOT shall identify, for 60 days, Electric Service Identifiers (ESI IDs) acquired in a Mass Transition to a Provider of Last Resort (POLR) so that Customers that switch from the POLR are not charged for an out-of-cycle meter read. This RMGRR also implements changes necessary to expedite the Customer switching process. References to Affiliated Retail Electric Provider (AREP) were also removed from Section 9, Appendix G.This RMGRR also proposes non-substantive administrative changes, such as correcting acronym and defined term usage and section references. These are shown below with the author "ERCOT Market Rules."
Reason: To facilitate ERCOT compliance with PUCT Project No. 35769, Rulemaking Relating to Providers of Last Resort, and Project No. 36536, Rulemaking to Expedite Customer Switch Timelines.

Key Documents