PGRR141

Summary

Title Large Load Interconnection Study Reform for Substantiated Load
Next Group
Next Step
Status Withdrawn

Action

Date Gov Body Action Taken Next Steps
02/05/2026 ROS Deferred/Tabled ROS for consideration

Voting Record

Date Gov Body Motion Result
02/05/2026 ROS To table PGRR141 and refer the issue to the Planning Working Group (PLWG) Passed

Background

Status: Withdrawn
Date Posted: Dec 31, 2025
Sponsor: Joint Sponsors
Urgent: No
Sections: 9.3.1
Description: This Planning Guide Revision Request (PGRR) enables more efficient Large Load studies, approvals, and subsequent transmission planning by allowing a Regional Planning Group (RPG) review to be used in place of a separate Large Load Interconnection Study (LLIS) when evaluating a substantiated Large Load interconnection.
Reason: Strategic Planning Objective 1

Key Documents