PGRR141

Summary

Title Large Load Interconnection Study Reform for Substantiated Load
Next Group ROS
Next Step ROS for language consideration
Status Pending

Action

Date Gov Body Action Taken Next Steps
No updates have been made to this issue.

Voting Record

Date Gov Body Motion Result
No updates have been made to this issue.

Background

Status: Pending
Date Posted: Dec 31, 2025
Sponsor: Joint Sponsors
Urgent: No
Sections: 9.3.1
Description: This Planning Guide Revision Request (PGRR) enables more efficient Large Load studies, approvals, and subsequent transmission planning by allowing a Regional Planning Group (RPG) review to be used in place of a separate Large Load Interconnection Study (LLIS) when evaluating a substantiated Large Load interconnection.
Reason: Strategic Planning Objective 1