Summary
| Title | Large Load Interconnection Study Reform for Substantiated Load |
|---|---|
| Next Group | ROS |
| Next Step | ROS for consideration |
| Status | Pending |
Action
| Date | Gov Body | Action Taken | Next Steps |
|---|---|---|---|
| 02/05/2026 | ROS | Deferred/Tabled | ROS for consideration |
Voting Record
| Date | Gov Body | Motion | Result |
|---|---|---|---|
| 02/05/2026 | ROS | To table PGRR141 and refer the issue to the Planning Working Group (PLWG) | Passed |
Background
| Status: | Pending |
|---|---|
| Date Posted: | Dec 31, 2025 |
| Sponsor: | Joint Sponsors |
| Urgent: | No |
| Sections: | 9.3.1 |
| Description: | This Planning Guide Revision Request (PGRR) enables more efficient Large Load studies, approvals, and subsequent transmission planning by allowing a Regional Planning Group (RPG) review to be used in place of a separate Large Load Interconnection Study (LLIS) when evaluating a substantiated Large Load interconnection. |
| Reason: | Strategic Planning Objective 1 |
Key Documents
Dec 31, 2025 - docx - 39.1 KB
Feb 2, 2026 - docx - 35.4 KB
Feb 4, 2026 - docx - 23.5 KB
Feb 5, 2026 - xls - 137.5 KB
Feb 5, 2026 - docx - 40.7 KB