MIS LOG IN

PGRR091

Summary

Title FIS Application Completion 60-Day Limit
Next Group
Next Step
Status Approved on 08/19/2021
Effective Dates
09/01/2021

Action

Date Gov Body Action Taken Next steps
08/19/2021 PUCT Approved
08/10/2021 BOARD Recommended for Approval PUCT for consideration
07/28/2021 TAC Recommended for Approval Revision Request Consideration
07/08/2021 ROS Recommended for Approval Revision Request Consideration
06/03/2021 ROS Recommended for Approval Impact Analysis Consideration

Voting Record

Date Gov Body Motion Result
08/19/2021 PUCT to approve PGRR091 and accompanying ERCOT Market Impact Statement as presented in Project No. 52307 Passed
08/10/2021 BOARD To recommend approval of PGRR091 as recommended by TAC in the 7/28/21 TAC Report Passed
07/28/2021 TAC to recommend approval of PGRR091 as recommended by ROS in the 7/8/21 ROS Report; and the Revised Impact Analysis Passed
07/08/2021 ROS to endorse and forward to TAC the 6/3/21 ROS Report and the Impact Analysis for PGRR091 with a recommended priority of 2022 and rank of 3530 Passed
06/03/2021 ROS to recommend approval of PGRR091 as revised by ROS Passed

Background

Status: Approved
Date Posted: May 18, 2021
Sponsor: ERCOT
Urgent: No
Sections: 5.3, 5.4.2
Description: This Planning Guide Revision Request (PGRR) establishes a limit for Interconnecting Entities (IEs) to complete an application to request a Full Interconnection Study (FIS) within 60 days of submittal. An FIS will be considered not to have been requested if the application is not completed within 60 days.
Reason: Addresses current operational issues

Key Documents

Related Content