Summary

Title Remedial Action Scheme Planning Assumptions
Next Group
Next Step
Status Approved on 02/09/2021
Effective Dates
03/01/2021

Action

Date Gov Body Action Taken Next steps
02/09/2021 BOARD Approved
01/27/2021 TAC Recommended for Approval Revision Request Consideration
12/03/2020 ROS Recommended for Approval Revision Request Consideration
11/05/2020 ROS Recommended for Approval Impact Analysis Consideration
10/08/2020 ROS Deferred/Tabled Language Consideration

Voting Record

Date Gov Body Motion Result
02/09/2021 BOARD to approve PGRR087 as recommended by TAC in the 1/27/21 TAC Report Passed
01/27/2021 TAC to recommend approval of PGRR087 as recommended by ROS in the 12/3/20 ROS Report Passed
12/03/2020 ROS to endorse and forward to TAC the 11/5/20 ROS Report and the Impact Analysis for PGRR087 Passed
11/05/2020 ROS to recommend approval of PGRR087 as submitted Passed
10/08/2020 ROS to table PGRR087 and refer the issue to PLWG Passed

Background

Status: Approved
Date Posted: Sep 23, 2020
Sponsor: ERCOT
Urgent: No
Sections: 3.1.4.1.1, 4.1.1.2
Description: This Planning Guide Revision Request (PGRR) clarifies that Remedial Action Schemes (RASs) should not be relied upon to resolve planning criteria violations.
Reason: Other: Clarifies and codifies transmission planning practices in regards to modeling Remedial Action Schemes.