MIS LOG IN

NPRR575

Summary

Title Clarification of the RUC Resource Buy-Back Provision for Ancillary Services
Next Group
Next Step
Status Approved on 12/10/2013
Effective Dates
01/07/2014

Action

Date Gov Body Action Taken Next steps
12/10/2013 BOARD Approved
12/03/2013 TAC Recommended for Approval ERCOT Board consideration of NPRR575
11/21/2013 PRS Recommended for Approval TAC consideration of NPRR575

Voting Record

Date Gov Body Motion Result
12/10/2013 BOARD To approve NPRR575 as recommended by TAC in the 12/3/13 TAC Report. Passed
12/03/2013 TAC To recommend approval of NPRR575 as recommended by PRS in the 11/21/13 PRS Report with a recommended priority of 2013 and rank of 365. Passed
11/21/2013 PRS to recommend approval of NPRR575 as revised by PRS. Passed

Background

Status: Approved
Date Posted: Oct 23, 2013
Sponsor: GDF Suez NA Inc.
Urgent: Yes
Sections: 3.9.1, 6.4.6, 6.5.7.6.1
Description: This Nodal Protocol Revision Request (NPRR) clarifies the use of Regulation Service by Generation Resources electing to use the Reliability Unit Commitment (RUC) Resource buy-back provision, which was added to the Protocols by NPRR416, and proposes new language to allow carrying of Regulation Service on Generation Resources exercising the RUC Resource buy-back provision upon system implementation.
Reason: As amended by NPRR416, the Protocols are unclear as to whether a Qualified Scheduling Entity (QSE) may carry Regulation Service on a Generation Resource for any hours during which the QSE has already bought back a RUC commitment for the Generation Resource (ONOPTOUT Resource Status). The changes contained herein are intended to clarify that a Generation Resource telemetering an ONOPTOUT Resource Status may provide Regulation Service. However, because this functionality would require further system changes, and because it is preferable to implement the Resource buy-back provision as soon as possible, the Protocols should be clarified to prohibit QSEs from carrying Regulation Service on Resources with an ONOPTOUT Resource Status until ERCOT can implement the system changes allowing Regulation Service to be carried on a Resource with ONOPTOUT status.

Key Documents

Related Content