NPRR522

Summary

Title Adjustment of Demand Response Performance for Distribution Losses (formerly "Adjustment of Demand Response Performance for T&D Losses ")
Next Group
Next Step
Status Approved on 07/16/2013
Effective Dates
08/01/2013

All sections except for Section 3.14.3.3(3)(a)

10/01/2013

Section 3.14.3.3(3)(a)

Action

Date Gov Body Action Taken Next steps
07/16/2013 BOARD Approved
06/06/2013 TAC Recommended for Approval ERCOT Board Consideration
05/16/2013 PRS Recommended for Approval
04/18/2013 PRS Recommended for Approval PRS IA Review
03/21/2013 PRS Recommended for Approval PRS IA Review

Voting Record

Date Gov Body Motion Result
07/16/2013 BOARD To approve NRR522 as recommended by TAC in the 6/6/13 TAC Report Passed
06/06/2013 TAC To recommend approval of NPRR522 as recommended by PRS in the 5/16/13 PRS Report Passed
05/16/2013 PRS To endorse and forward the 4/18/13 PRS Report and Impact Analysis for NPRR522 to TAC Passed
04/18/2013 PRS To recommend approval of NPRR522 as amended by the 4/18/13 CPS Energy comments and as revised by PRS Passed
03/21/2013 PRS To recommend approval of NPRR522 as amended by the 3/14/13 DSWG comments and as revised by PRS Passed

Background

Status: Approved
Date Posted: Feb 25, 2013
Sponsor: DSWG
Urgent: No
Sections: 3.7.1.2, 3.9.1, 3.14.3.3, 4.4.7.2.1, 8.1.1.2, 13.3
Description: This Nodal Protocol Revision Request (NPRR) addresses inequality by adjusting the metered Load of demand response Resources for Distribution Losses.
Reason: This NPRR would adjust the quantity of demand response that can be offered into Ancillary Services and Emergency Response Services (ERS) to include an adjustment for line losses.