MIS LOG IN

NPRR460

Summary

Title WGR Ramp Rate Limitations
Next Group
Next Step
Status Approved on 11/13/2012
Effective Dates
12/01/2012

Action

Date Gov Body Action Taken Next steps
11/13/2012 BOARD Approved
09/07/2012 TAC Recommended for Approval Board Consideration
08/23/2012 PRS Recommended for Approval TAC Consideration
07/19/2012 PRS Recommended for Approval IA Review
05/17/2012 PRS Deferred/Tabled PRS Language Consideration

Voting Record

Date Gov Body Motion Result
11/13/2012 BOARD To approve NPRR460 as recommended by TAC in the 9/7/12 TAC Report Passed
09/07/2012 TAC To recommend approval of NPRR460 as recommended by PRS in the 8/23/12 PRS Report Passed
08/23/2012 PRS To endorse and forward the 7/19/12 PRS Report as amended by the 8/16/12 ERCOT comments and as revised by PRS and the Impact Analysis for NPRR460 to TAC Passed
07/19/2012 PRS To recommend approval of NPRR460 as revised by PRS Passed
05/17/2012 PRS To table NPRR460 and to refer the issue to ROS Passed

Background

Status: Approved
Date Posted: May 2, 2012
Sponsor: E.ON Climate & Renewables
Urgent: No
Sections: 6.5.7.10
Description: This Nodal Protocol Revision Request (NPRR) increases the Wind-powered Generation Resource (WGR) ramp rate limitation from 10% per minute of nameplate rating to a five minute average of 20% per minute of nameplate rating with no individual minute exceeding 25%..
Reason: This revision allows WGRs to be fully dispatched on or fully curtailed off in one Security-Constrained Economic Dispatch (SCED) dispatch interval. This would allow for a more efficient dispatch of Resources and more precise curtailment instructions to WGRs.