This NPRR enables ERCOT to perform a “Batch Alpha” interconnection study for Large Loads by using an existing process (the Regional Planning Group (RPG) process) with clearly defined timelines and inclusion criteria. Importantly, this will allow ERCOT to achieve aggressive timelines for implementation without requiring the need for a good cause exception to the Protocols.