Summary

Title Estimated Demand Response Data
Next Group
Next Step
Status Approved on 07/31/2025

Action

Date Gov Body Action Taken Next Steps
07/31/2025 PUCT Approved
06/24/2025 BOARD Recommended for Approval PUCT for consideration
05/28/2025 TAC Recommended for Approval Board for consideration
05/14/2025 PRS Recommended for Approval TAC for consideration
03/12/2025 PRS Deferred/Tabled PRS for consideration
02/12/2025 PRS Recommended for Approval PRS for Impact Analysis consideration
05/09/2024 PRS Deferred/Tabled PRS for consideration

Voting Record

Date Gov Body Motion Result
07/31/2025 PUCT To approve NPRR1226 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization Passed
06/24/2025 BOARD To recommend approval of NPRR1226 as recommended by TAC in the 5/28/25 TAC Report Passed
05/28/2025 TAC To recommend approval of NPRR1226 as recommended by PRS in the 5/14/25 PRS Report as revised by TAC Passed
05/14/2025 PRS To endorse and forward to TAC the 3/12/25 PRS Report as revised by PRS and 5/5/25 Impact Analysis for NPRR1226 with a recommended priority of 2026 and rank of 4770 Passed
03/12/2025 PRS To table NPRR1226 Passed
02/12/2025 PRS To recommend approval of NPRR1226 as amended by the 2/11/25 ERCOT comments Passed
05/09/2024 PRS To table NPRR1226 and refer the issue to WMS Passed

Background

Status: Approved
Date Posted: Apr 23, 2024
Sponsor: ERCOT Steel Mills
Urgent: No
Sections: 2.1, 2.2, 6.3.2, and 6.5.7.1.13
Description: This Nodal Protocol Revision Request (NPRR) directs ERCOT to prepare and publish estimated Demand response data showing aggregated State Estimated Load (SEL) load points selected by ERCOT. The selection of Loads to be aggregated for the report will be based on periodically updated off-line analysis of the frequency and magnitude of reductions observed in historical State Estimator load data that is associated with market signals such as Locational Marginal Prices (LMPs), high levels of summer month ERCOT load, ERCOT-wide appeal(s) through public voluntary energy appeal, or other ERCOT actions.
Reason: Strategic Plan Objective 2