Summary

Title Section 24, Synchronization of Zonal Protocols
Next Group
Next Step
Status Approved on 06/17/2008
Effective Dates
12/01/2010

or per the Nodal Protocol Transition Plan http://www.ercot.com/mktrules/protocols (07/01/08 Nodal Protocols Library)

Action

Date Gov Body Action Taken Next steps
06/17/2008 BOARD Approved
06/05/2008 TAC Recommended for Approval ERCOT Board Review
05/22/2008 PRS Recommended for Approval TAC consideration of NPRR106
04/18/2008 PRS Recommended for Approval Impact Analysis Review
03/20/2008 PRS Referred

Voting Record

Date Gov Body Motion Result
06/17/2008 BOARD To approve NPRR106 as recommended by TAC. Passed
06/05/2008 TAC To recommend approval of NPRR106 as recommended by PRS. Passed
05/22/2008 PRS To endorse and forward the PRS Recommendation Report, as amended by ERCOT Staff comments dated 4/30/08, and Impact Analysis to TAC Passed
04/18/2008 PRS Recommend approval of NPRR106 as amended by TPTF comments and as revised by PRS with instruction to ERCOT Staff that "section specific" definitions and acronyms be inserted into Section 2, Definitions and Acronyms, through a separate NPRR. Passed
03/20/2008 PRS To refer NPRR106 to the TPTF for consideration. Passed

Background

Status: Approved
Date Posted: Feb 26, 2008
Sponsor: ERCOT
Urgent: No
Sections: Zonal Protocol Section 24
Description: This Nodal Protocol Revision Request (NPRR) synchronizes zonal Protocol Section 24 with the current Nodal Protocols.
Reason: Synchronization of remaining zonal Protocol sections with the Nodal Protocols.