Agenda
1. |
Antitrust Admonition |
M. Henson |
2. |
Approval of Minutes (Vote) |
M. Henson |
February 8, 2018 |
||
3. |
TAC and Board Reports |
M. Henson |
4. |
Project Update and Summary of Project Priority List (PPL) Activity to Date |
T. Anderson |
Impact Analysis Recommendations and Statistics |
||
5. |
Annual Review of Other Binding Document List (Vote) |
M. Henson |
6. |
Urgency Vote(s) (Vote) |
M. Henson |
NPRR868, As-Built Hub and Load Zone Calculation |
||
7. |
Review PRS Reports, Impact Analyses, and Prioritization (Vote) (*) denotes no impact |
M. Henson |
NPRR853, Availability of ERCOT Estimated Interval Meter Data |
||
NPRR858, Provide Complete Current Operating Plan (COP) Data |
||
NPRR864, RUC Modifications to Consider Market-Based Solutions |
||
NPRR865, Publish RTM Shift Factors for Hubs, Load Zones, and DC Ties |
||
SCR793, SSR Related Telemetry for Transmission Service Provider (TSP) Operators |
||
SCR795, Addition of Intra-Hour Wind Forecast to GTBD Calculation |
||
8. |
Revision Requests Tabled at PRS (Possible Vote) |
M. Henson |
NPRR807, Day-Ahead Market Price Correction |
||
NPRR823, Amend the Definition of an Affiliate |
||
NPRR826, Mitigated Offer Caps for RMR Resources |
||
NPRR832, Disallow PTP Obligation Bids and DAM Energy Bids that Sink at Private Use Network Settlement Points Without a Load Distribution Factor - URGENT |
||
NPRR837, Regional Planning Group (RPG) Process Reform |
||
NPRR838, Updated O&M Cost for RMR Resources |
||
NPRR845, RMR Process and Agreement Revisions |
||
NPRR847, Exceptional Fuel Cost Included in the Mitigated Offer Cap |
||
NPRR848, Separate Clearing Prices for RRS |
||
NPRR849, Clarification of the Range of Voltage Set Points at a Generation Resource’s POI |
||
NPRR850, Market Suspension and Restart |
||
NPRR851, Procedure for Managing Disconnections for Bidirectional Electrical Connections at Transmission Level Voltages |
||
NPRR856, Treatment of OFFQS Status in Day-Ahead Make Whole and RUC Settlements |
||
NPRR857, Creation of Direct Current Tie Operator Market Participant Role |
||
NPRR862, Updates to Address Revisions under PUCT Project 46369 |
||
NPRR863, Creation of Primary Frequency Response Service Product and Revisions to Responsive Reserve |
||
9. |
Review of Revision Request Language (Vote) |
M. Henson |
NPRR866, Mapping Registered Distributed Generation and Load Resources to Transmission Loads in the Network Operations Model |
||
10. |
Resource Definition Task Force (RTF) |
D. Ricketts |
11. |
Other Business |
M. Henson |
Adjourn |
M. Henson |
Scheduled PRS Meetings
- Jan 18, 2018 - PRS Meeting
- Feb 08, 2018 - PRS Meeting
- Mar 08, 2018 - PRS Meeting
- Apr 12, 2018 - PRS Meeting
- May 10, 2018 - PRS Meeting
- Jun 14, 2018 - PRS Meeting
- Jul 19, 2018 - PRS Meeting
All information is posted as Public in accordance with the ERCOT Websites Content Management Corporate Standard.