Title RTC+B – Mitigated Offer Cap for Hydro Generation Resources
Next Group WMS
Next Step WMS for Impact Analysis consideration
Status Pending

Action

Date Gov Body Action Taken Next Steps
05/07/2025 WMS Recommended for Approval WMS for Impact Analysis consideration

Voting Record

Date Gov Body Motion Result
05/07/2025 WMS To recommend approval of VCMRR044 as submitted Passed

Background

Status: Pending
Date Posted: Apr 22, 2025
Sponsor: ERCOT
Urgent: No
Sections: Appendix 10
Description: This Verifiable Cost Manual Revision Request (VCMRR) adds a procedure to Appendix 10 for setting the variables used in the Mitigated Offer Cap (MOC) for hydro Generation Resources: setting Variable O&M (VOM) to the Real-Time System-Wide Offer Cap (RTSWCAP) and the incremental heat rate value to zero. These settings ensure that the MOC for such Resources is at least equal to or greater than the RTSWCAP.
Reason: ERCOT Board/PUCT Directive