MIS LOG IN

VCMRR044

Summary

Title RTC+B – Mitigated Offer Cap for Hydro Generation Resources
Next Group PUCT
Next Step PUCT for consideration
Status Pending

Action

Date Gov Body Action Taken Next Steps
09/22/2025 BOARD Recommended for Approval PUCT for consideration
07/30/2025 TAC Recommended for Approval Board for consideration
06/04/2025 WMS Recommended for Approval TAC for consideration
05/07/2025 WMS Recommended for Approval WMS for Impact Analysis consideration

Voting Record

Date Gov Body Motion Result
09/22/2025 BOARD To recommend approval of VCMRR044 as recommended by TAC in the 7/30/25 TAC Report Passed
07/30/2025 TAC To recommend approval of VCMRR044 as recommended by WMS in the 6/4/25 WMS Report Passed
06/04/2025 WMS To endorse and forward to TAC the 5/7/25 WMS Report and 4/22/25 Impact Analysis for VCMRR044 Passed
05/07/2025 WMS To recommend approval of VCMRR044 as submitted Passed

Background

Status: Pending
Date Posted: Apr 22, 2025
Sponsor: ERCOT
Urgent: No
Sections: Appendix 10
Description: This Verifiable Cost Manual Revision Request (VCMRR) adds a procedure to Appendix 10 for setting the variables used in the Mitigated Offer Cap (MOC) for hydro Generation Resources: setting Variable O&M (VOM) to the Real-Time System-Wide Offer Cap (RTSWCAP) and the incremental heat rate value to zero. These settings ensure that the MOC for such Resources is at least equal to or greater than the RTSWCAP.
Reason: ERCOT Board/PUCT Directive

Key Documents