PRR763

Summary

Title Use of WGRPP as Planned Operating Level in Day-Ahead Resource Plan for WGRs
Next Group
Next Step
Status Approved on 06/17/2008
Effective Dates
07/01/2008

Action

Date Gov Body Action Taken Next steps
06/17/2008 BOARD Approved
06/05/2008 TAC Recommended for Approval Board of Directors consideration
05/22/2008 PRS Recommended for Approval TAC consideration

Voting Record

Date Gov Body Motion Result
06/17/2008 BOARD To approve PRR763 as recommended by TAC. Passed
06/05/2008 TAC To recommended approval of PRR763 as revised by TAC. Passed
05/22/2008 PRS To recommend approval of PRR763 as modified by PRS. Passed

Background

Status: Approved
Date Posted: May 16, 2008
Sponsor: John Dumas on behalf of the Reliability and Operations Subcommittee (ROS)
Urgent: Yes
Sections: 2.1, Definitions, 2.2, Acronyms and 4.4.15, QSE Resource Plans
Description: This Protocol Revision Request (PRR) allows Qualified Scheduling Entities (QSEs) representing Wind-powered Generation Resources (WGR) to use an ERCOT provided Wind-powered Generation Resource Power Potential (WGRPP) forecast as the planned operating level in the Resource Plan.
Reason: Historically, ERCOT has not provided a wind-powered generation forecast for either the total ERCOT System or for the individual WGRs. Also, when performing RPRS studies, the planned operating level in the Resource Plans for WGRs is treated in the same manner as all other Resources. WGRs will continue to be treated in the same fashion; however, this PRR will allow ERCOT to perform Day Ahead RPRS procurement using a conservative forecast of the output from WGRs.