MIS LOG IN

PGRR111

Summary

Title Related to NPRR1191, Registration, Interconnection, and Operation of Customers with Large Loads; Information Required of Customers with Loads 25 MW or Greater
Next Group ROS
Next Step ROS for consideration
Status Pending

Action

Date Gov Body Action Taken Next steps
09/07/2023 ROS Deferred/Tabled ROS for consideration

Voting Record

Date Gov Body Motion Result
09/07/2023 ROS To table PGRR111 Passed

Background

Status: Pending
Date Posted: Aug 1, 2023
Sponsor: ERCOT
Urgent: No
Sections: 2.1, 4.1.1.2, 5.2.10 (new), 5.3.5, 6.1, 6.6 (new), 6.6.1 (new), 6.6.2 (new), 6.6.3 (new), 6.6.4 (new), 7.1, 9 (new), 9.1 (new), 9.2 (new), 9.2.1 (new), 9.2.2 (new), 9.2.3 (new), 9.2.4 (new), 9.3 (new), 9.3.1 (new), 9.3.2 (new), 9.3.3 (new), 9.3.4 (new), 9.3.4.1 (new), 9.3.4.2 (new), 9.3.4.3 (new), 9.4 (new), 9.5 (new), 9.5.1 (new), 9.5.2 (new), 9.5.3 (new), 9.6 (new)
Description: This Planning Guide Revision Request (PGRR) creates a new process for studying the reliability impacts of all Large Loads (those 75MW or more) that will be interconnected within 24 months. As with the Full Interconnection Study (FIS) required for proposed Generation Resources, this PGRR requires a Large Load Interconnection Study (LLIS) for each new Large Load meeting applicability requirements that is proposed to interconnect to the ERCOT System. Like the FIS, the LLIS will consist of a similar suite of studies conducted by one or more affected Transmission Service Providers (TSP). This PGRR describes these studies in detail and establishes timelines for the review of these studies and the completion of other steps in the interconnection process. This PGRR requires a Customer proposing to interconnect such a Load—referred to as a “Large Load Interconnecting Entity”—to initiate such a request through ERCOT’s Resource Integration and Ongoing Operations (RIOO) system, which will leverage the efficiency of this existing tool to enable ERCOT and affected TSPs to submit, review, and confirm completion of the studies that are needed. This PGRR also requires some Large Loads to be evaluated as part of the existing quarterly stability assessment. This PGRR also adds additional Reliability Performance Criteria for the inclusion of Large Loads in planning studies.
Reason: Strategic Plan Objective 1
Related Content